07/09/2025

Аrsky Branch

07/07/2025

Аrsky Branch

07/07/2025

Аrsky Branch

07/05/2025

Menzelinsky Branch

Aktanysh – Musliumovo: 5+840 - 8+790 (Aktanyshsky district)

Works are finished.

07/05/2025

Menzelinsky Branch

M-7 “Volga” – Stary Irkenyash – Tatarskaya Mushuga: 6+591 - 8+591 (Menzelinsky district)

Works are finished.

07/04/2025

Menzelinsky Branch

Musliumovo – Staroye Saitovo: 18+200 - 20+100 (Musliumovsky district)

Construction of surface course with grade 8 stone mastics is finished.

07/04/2025

Аrsky Branch

Mamadysh – Tiulyachi:  45+050 - 49+250 (Tiulyachinsky district)

Milling of the asphaltic road surface course with recycler (0.15 m deep).

07/04/2025

Аrsky Branch

Satyshevo – Bogatye Saby: 0+240 - 0+750 (Tiulyachinsky district)

Construction of leveling course with А16Нт asphaltic mix.

06/26/2025

Аrsky Branch

Arsk – Mari El Republic limits: 11+300 - 14+910 (Arsky district)

Works are finished.

06/25/2025

Menzelinsky Branch

Tiukovo – Tatarskiye Yamaly: 10+919 - 17+532 (Aktanyshsky district)

Construction of subsoil and base course with sand-and-gravel mix is in progress.

06/25/2025

Menzelinsky Branch

Musliumovo – Saklov-Bash – Yultimerovo: 30+700 - 32+700 (Sarmanovsky district)

Construction of surface course with grade 8 stone mastics is finished.

06/24/2025

Nizhnekamsky Branch

Naberezhnye Chelny – Zayinsk – Almetyevsk: 0+130 - 10+130 (Tukayevsky district)

Construction of surface course with grade 16 stone mastics mix is finished.

06/18/2025

Menzelinsky Branch

Tiukovo – Tatarskiye Yamaly: 10+919 - 17+532 (Aktanyshsky district)

Strengthening of base course with sand-and-gravel mix using recycler equipment. 

06/18/2025

Menzelinsky Branch

Aktanysh – Musliumovo: 5+840 - 8+790 (Aktanyshsky district)

Construction of surface course with grade 8 stone mastics is finished.

06/10/2025

Suburban Branch

Sorochy Gory – Shaly: 0+120 - 1+424 (Rybno-Slobodsky district)

Construction of surface course with grade 16 stone mastics is finished.

06/10/2025

Nizhnekamsky Branch

Chistopol – Nizhnekamsk: 78+977 - 80+977 (Nizhnekamsky district)

Construction of surface course with grade 16 stone mastics mix is finished.

06/09/2025

Menzelinsky Branch

Aktanysh – Musliumovo: 5+840 - 8+790 (Aktanyshsky district)

Construction of leveling course with А16Нн asphaltic mix is finished.

06/06/2025

Buinsky Branch

Tatarskiye Shatrashany – Ulyanovsk oblast limits: 0+000 - 0+637 (Drozhzhanovsky district)

Construction of surface course with grade 8 stone mastics in progress.

06/05/2025

Sabinsky Branch

Access road to construction site of new Medical Centre for Cardiovascular Surgery “Sabinsky central regional hospital”: 0+000 - 15+260 (Sabinsky district)

Construction of 0.04 m thick RAU-8 asphalt-concrete surface course is in progress.

06/04/2025

Аrsky Branch

Mamadysh – Tiulyachi:  45+050 - 49+250 (Tiulyachinsky district)

Milling of pavement with recycler equipment. 

06/04/2025

Apastovsky Branch

Road maintenance works on local roads in Kamsko-Ustyinsky district of the Republic of Tatarstan (Kamsko-Ustyinsky district)

Workers of JSC “Tatavtodor” mow the grass off the slopes and roadsides with tractor-mounted mower. 

06/03/2025

Apastovsky Branch

P-241 Kazan – Ulyanovsk (Federal auto roads district)

 Summer road maintenance works in progress. 

06/02/2025

Аrsky Branch

Arsk – Mari El Republic limits: 11+300 - 14+910 (Arsky district)

Strengthening of roadsides.

06/02/2025

Apastovsky Branch

“Karatun – Cheremshan – Bolshoye Podberezye” – Deushevo – Kushtovo: 9+545 - 11+460 (Arsky district)

Construction of base course with А16Нн asphaltic mix is finished.

05/31/2025

Apastovsky Branch

“Kazan – Ulyanovsk” – Kliuchischy: 0+000 - 1+890 (Verkhneuslonsky district)

Construction of base course with А16Нн asphaltic mix is finished.

05/30/2025

Buinsky Branch

Lyashevo – Yambukhtino: 0+000 - 5+300 (Tetiushsky district)

Stabilization of soil with lime and construction of base course with M-400 macadam.

05/30/2025

Buinsky Branch

Buinsk – Tetiushy: 12+009 - 16+000 (Tetiushsky district)

Removing of the grass layer, breaking of the asphaltic surface (regeneration, 1st pass) and construction of earthen roadbed.

05/30/2025

Buinsky Branch

Apastovo – Tetiushy: 31+000 - 31+750 (Tetiushsky district)

Construction of leveling course is in progress.

05/30/2025

Buinsky Branch

Buinsk – Yalchiki: 2+080 - 2+860; 3+955 - 6+275 (Buinsky district)

Construction of widening pits and macadam-and-mastics (grade 8) surface course.

05/30/2025

Aksubaevsky Branch

Chistopol – Aksubayevo – Nurlat: 80+073 - 82+173 (Aksubayevsky district)

Construction of surface course with grade 8 stone mastics is in progress.

05/30/2025

Menzelinsky Branch

M-7 “Volga” – Stary Irkenyash – Tatarskaya Mushuga: 6+591 - 8+591 (Menzelinsky district)

Construction of leveling course with А16Нн asphaltic mix is finished.

05/29/2025

Apastovsky Branch

Road network in Tashevka settlement: 0+000 - 2+980 (Verkhneuslonsky district)

Construction of surface course with А16Вл asphaltic mix is finished.

05/28/2025

Buinsky Branch

Tatarskiye Shatrashany – Ulyanovsk oblast limits: 0+000 - 0+637 (Drozhzhanovsky district)

Construction of roadbed using cold recycling method with addition of M800 macadam (grade 16-31.5) and 2% of portland cement.

05/28/2025

Suburban Branch

M-7 “Volga” Moscow-Vladimir-Nizhniy Novgorod-Kazan-Ufa: 878+005 - 940+265; 970+000 - 986+811 (Rybno-Slobodsky district)

Construction of wearing course with SMA-11 and PG-34 bitumen adhesive.  

05/28/2025

Menzelinsky Branch

Tiukovo – Tatarskiye Yamaly: 10+919 - 17+532 (Aktanyshsky district)

Stabilization and strengthening of soil with lime.

05/27/2025

Аrsky Branch

Arsk – Mari EL Republic limits: 11+300 - 14+910 (Arsky district)

Construction of surface course with stone mastics (grade 8, thickness 0.04 m).

05/26/2025

Aksubaevsky Branch

Access road to barnyard near Aksubayevo settlement: 0+000 – 0+590 (Aksubayevsky district)

Construction of base course with А22Нл asphaltic mix.

05/23/2025

Аrsky Branch

Road maintenance works on local roads in Arsky district of the Republic of Tatarstan (Arsky district)
Mowing of the grass with tractor-mounted and motor trimmers.

05/22/2025

Аrsky Branch

Koshar – Kliuchi-Sap: 11+524 - 12+924 (Atninsky district)

Strengthening of roadsides with M-400 macadam, layer thickness 0.1 m.

05/22/2025

Аrsky Branch

Bolshaya Atnya – Chepchugy: 12+750 - 14+455 (Atninsky district)

Construction of base course using cold regeneration method with Caterpillar RM-500 recycler, layer thickness 0.20 m.

05/20/2025

Menzelinsky Branch

Musliumovo – Tatarskiy Shugan: 0+000 - 1+286 (Musliumovsky district)

Construction of base course with А32Нн asphaltic mix is finished.

05/17/2025

Sabinsky Branch

Kazan – Shemordan: 97+487 - 100+927 (Sabinsky district)

Construction of surface course with stone mastics (grade 8, thickness 0.04 m).

05/16/2025

Аrsky Branch

Koshar – Kliuchi-Sap: 11+524 - 12+924 (Atninsky district)

Construction of surface course with stone mastics (grade 8).

05/16/2025

Suburban Branch

M7 “Volga” Moscow-Vladimir-Nizhniy Novgorod-Kazan-Ufa: 878+005 - 940+265; 970+000 - 986+811 (Rybno-Slobodsky district)

Construction of wearing course with SMA-11 using bituminous adhesive PG-34.

05/16/2025

Menzelinsky Branch

Musliumovo – Staroye Saitovo: 18+200 - 20+100 (Musliumovsky district)

Construction of leveling course with А16Нн asphalt-concrete mix is finished.

05/16/2025

Menzelinsky Branch

Musliumovo – Tatarskiy Shugan: 0+000 - 1+286 (Musliumovsky district)

Construction of base course using cold regeneration method with RM-500 recycler with addition of 2% of ЦЕМ I-42.5Н cement is finished.

05/15/2025

Аrsky Branch

Arsk – Mari EL Republic limits: 11+300 - 14+910 (Arsky district)

Construction of leveling course with А16Нн asphalt-concrete mix.

05/14/2025

Apastovsky Branch

“Kazan – Ulyanovsk” – Kamskoye Ustye: 54+572 - 56+615 (Kamsko-Ustyinsky district)

Construction of leveling course with А16Нн asphalt-concrete mix is finished.

05/13/2025

Аrsky Branch

Koshar – Kliuchi-Sap: 11+524 - 12+924 (Atninsky district)

Construction of leveling course with А16Нн asphalt-concrete mix.

05/13/2025

Apastovsky Branch

“Karatun – Cheremshan – Bolshoye Podberezye” – Deushevo – Kushtovo: 9+545 - 11+460 (Apastovsky district)

Construction of water pipes in progress.

05/12/2025

Menzelinsky Branch

Musliumovo – Tatarskiy Shugan: 0+000 - 1+286 (Musliumovsky district)

Construction of base course using cold regeneration method with RM-500 recycler with addition of M-800 macadam is finished.

05/12/2025

Mamadyshsky Branch

M7 “Volga” Moscow-Vladimir-Nizhniy Novgorod-Kazan-Ufa: 878+005 - 940+265; 970+000 - 986+811 (Rybno-Slobodsky district)

Milling of uplifts and rut roughness, construction of wearing surface.

05/08/2025

Apastovsky Branch

Road maintenance on local roads in Kamsko-Ustyinsky district (Kamsko-Ustyinsky district)

Workers form Apastovsky branch had finished reconstruction of worn-out road surfaces in Kamsko-Ustyinsky municipal district of the Republic of Tatarstan.

05/08/2025

Аrsky Branch

Koshar – Kliuchi-Sap: 11+524 - 12+924 (Atninsky district)

Milling of asphalted surface.

05/07/2025

Suburban Branch

Sredneye Devyatovo – Tatarskiy Yantyk: 1+000 - 8+816; 11+018 - 12+555 (Laishevsky district)

Construction of base course using cold regeneration method with recycler with addition of water, enriched sand-and-gravel mix, and portland cement.  

05/07/2025

Аrsky Branch

Arsk – Mari EL Republic limits: 11+300 - 14+910 (Arsky district)

Milling of asphalted surface and levelling up to mark.